Theatre Arts Seismic Retrofit

Project Vitals 

 
Planned Construction DurationFall 2018 - Fall 2019
Project Budget$17,884,000
Funding SourceCSU Chancellor's Office via State Revenue Bonds
Humboldt Project ManagerJason Baugh
Project ArchitectSuarez-Kuehne Architecture
Project ContractorThompson Builders Corporation

  ← Back to Capital Projects list

Important Updates & Information

Theatre Arts Seismic Retrofit Scope of Work

Theatre Arts Seismic Retrofit Project Schedule

  • The CSU Seismic Review Board classified the University’s Theatre Arts Building as a priority one seismic retrofit project as a result of a number of studies completed over the past several years.  The primary objectives of the project, which outline the core achievements required of the funding per the Chancellor’s Office, include completion of seismic elements to achieve the seismic strengthening required to mitigate the hazards identified by the Review Board, installation of code compliance upgrades triggered by implementing the seismic elements, and improvement of the operational cost efficiency of the campus from a facilities perspective.  Completion of the Theater Arts Building will be on time, July 26th 2019 and ensure that we can complete move in activities and have JVD for events and programs for the Fall 2019 semester. There will be some continuing work at the Theater Arts Building running through August 23rd that does not impact the building occupants.

Phase I (Spring/Summer 2017)

  • Seismic Coefficient changed - triggering redesign of the retrofit project  

Phase II (Fall 2017-Fall 2018)

  • Project Implementation Plan created to address every space that will be impacted from the construction
  • Development and execution of the Campus Events Field Project and the Jenkins Hall Move; these spaces will provide accommodations for most of the relocated classes, programs, services, staff, and faculty impacted during the construction project
  • Redesign of project scope to reflect the current seismic code changes
  • Permitting of final construction documents
  • Solicit bids for the construction of the seismic retrofit project 

Phase III (Fall 2018-Fall 2019)

  • Construction Phase
  • Seismic retrofit project work scope to include:
    • Strengthening the existing columns and existing shear walls
    • Adding additional steel bracing through the building
    • Upsizing the size of the concrete pilasters on the fly tower
    • Upgrading the ADA parking, the accessible path of travel, and restrooms
    • Upgrade the HVAC system and lighting throughout the building 

Phase IV (Summer-Fall 2019)

  • Construction Substationally Completed
  • Reoccupy TA Building