Breadcrumb
XUC005 UC Substation
Project Vitals
Planned Construction Duration | Spring 2019 |
Project Budget | |
Funding Source | University Center Funding |
Humboldt Project Manager | Bruce Ryan |
Project Engineeer | Silas O'Brian |
Project Contractor | Converse Construction |
Substation Replacement Scope ofWork
The project includes feasibility studies and electrical engineering through the building permit phase, in preparation for future improvement projects at the University Center
Important Updates & Information
- Substation Replacement complete
- Out to bid-pre bid meeting on 1/7/2019-bids due 1/23/2019
- Rough-In completed 12/21/2018
- Programming and Commissioning to begin January 2019
- Johnson Controls has completed their rough in electrical and plumbing. They are moving into mechanical rooms to start completing/commissioning the new controls.