background 0background 1background 2background 3

The CSU has a new policy on freedom of expression. Learn more.

Breadcrumb

XUC005 UC Substation

Project Vitals

Planned Construction DurationSpring 2019
Project Budget 
Funding SourceUniversity Center Funding
Humboldt Project ManagerBruce Ryan
Project EngineeerSilas O'Brian
Project ContractorConverse Construction

Substation Replacement Scope ofWork

The project includes feasibility studies and electrical engineering through the building permit phase, in preparation for future improvement projects at the University Center

Important Updates & Information

  • Substation Replacement complete
  • Out to bid-pre bid meeting on 1/7/2019-bids due 1/23/2019 
    • Rough-In completed 12/21/2018
    • Programming and Commissioning to begin January 2019
    • Johnson Controls has completed their rough in electrical and plumbing. They are moving into mechanical rooms to start completing/commissioning the new controls.